For two days, April 8 and 9, 2015, the Sales and Operations
Departments of Freyssinet, Inc. met to exchange experiences, improvements
made within the several departments, present special project works and
new operation techniques.
The highlight of the meeting was the visit of the Boggy
Creek interchange job site.... John Newton, Project Manager of this project, presented to the Group the work provided by Freyssinet, Inc. as well as its unique challenges: Boggy Creek consist of three each “flyover” ramps in the general vicinity of the Orlando International Airport. The ramps consists of 90 each precast U-girders. Freyssinet, Inc. is performing all post-tensioning operations at the precast facility and jobsite, providing approximatively 500 tons of 0.6” strand with tendon lengths in excess of 1000 ft. |
Boggy Creek - One of the flyover ramps
Boggy Creek - U Beams in place prior to stressing diaphragm pour
Boggy Creek - Opening for the stressing diaphragm pour
Boggy Creek - Scaffolding
Boggy Creek - Team on the Bridge